[Bijapur] Work on Kudgi thermal plant to begin on June 2

Source: DHNS


Bijapur, May 28 2012, DHNS:
Work on the much-delayed thermal power plant project is set to begin at last, with Union Minister for Power Sushilkumar Shidhe scheduled to lay the foundation-stone at Kudgi in the district on June 2. 

The first project to be taken up in the State by the National Thermal Power Corporation requires 3,500 acres of land, of which 1,923 acre has already been acquired.

The NTPC officials held a meeting with the farmers on Saturday and cleared the way for acquisition of rest of the land by agreeing to pay a special compensation of Rs two lakh per acre.

The total amount of compensation per acre will be Rs 7.25 lakh for dry land and Rs nine lakh for irrigated land, General Manager Asimkumar Samanth told Deccan Herald.

A project office has also been set up on the site where a 4,000-mw capacity plant will come up.  In the first phase, three units with a capacity of 800 mw each will be set up at an estimated cost of Rs 15,166 crore. In the second phase, two units with 800-mw capacity each will come up.

The NTPC has signed an agreement with two companies – Toshiba of Japan and Dusan of Korea – on purchase of equipment worth Rs 6,087 crore required for the project in the first phase, and 162 cusec of water will be supplied to the plant from the Almatti reservoir.

Coal will be supplied through railways and the Centre has been requested to provide infrastructure required for the same at the earliest, said Samanth.  The 2,400 mw power to be generated at the plant in the three units, will be distributed among Karnataka, Kerala, Tamil Nadu, Andhra Pradesh and Puduchery.

Friday, January 27, 2012

[Bijapur] Construction work for the proposed mega thermal power project at Kudgi in Bijapur district is likely to start soon

Source: Deccan Herald

Construction work for the proposed mega thermal power project at Kudgi in Bijapur district is likely to start soon as the state-owned power producer National Thermal Power Corporation (NTPC) has got the Ministry of Environment and Forests (MoEF) clearance for its stage one (3x800 MW) project.

File photoKudgi is the first plant to be set up in Karnataka by NTPC with a total installedLink capacity of 4,000 MW in two stages, with Phase 1 of 2,400 MW.
The Karnataka Industrial Area Development Board, nodal agency of the Karnataka Government to acquire land, had recently handed over 1,923 acres of land required for the main plant. Land acquisition for the rest 1,600 acres is in progress.

The NTPC Board of Directors recently cleared investment proposal to the tune of Rs 15,166 crore for setting up the project. NTPC would be awarding the main plant package and taking up other infrastructure development works shortly.

“The project will have super critical boilers and latest technology. Coal requirement will be met from NTPC’s own mine at Pakhri Barwadi in Jharkhand,” the statement said.

To meet the water requirement, Karnataka Government has approved 5.2 tmc of water per annum from the Almatti Dam, which is 18km from the plant site.

The proposed plant will have a capacity to generate 80 million units of power a day and 50 per cent of it will be supplied to Karnataka. The remaining units will be shared among other states like Andhra Pradesh, Tamil Nadu and Puducherry through the Central Grid.

The MoU for the mega project was signed between the Karnataka government, NTPC and the state-held Power Company of Karnataka Ltd in January 2009. Though the company had planned to start the works by the middle of last year, getting environment clearances delayed it till now.